FUSION AEROSPACE-GRADE PVD // TECHNICAL OPERATIONS DOSSIER
CHAMBER: 6.80 m³ | VACUUM TRAIN: 72 kW | BASE TARGET: 1.0×10⁻² Pa
MISSION OPERATIONS MANUAL // REV 2.0
1.9 m × 2.4 m Cathodic Arc PVD System
Precision engineering dossier for the Shenyang Youbida KT-1200 high-vacuum diffusion pump, 2 × 7.5 kW Roots boosters, 6 × 70 L/s (5.5 kW) Rotary Vane backing train, and 22 × SASH Arc Sources.
Chamber Envelope
Ø1.9m × 2.4m
6.80 m³ Volume
High Vacuum
50,000 L/s
KT-1200 (5×10⁻⁵ Pa)
Oil Charge
22 Liters
HFV-K3 (230–260°C)
KT-1200 Heater
24.0 kW
~36.5 A / ph (380V)
Cooling Water
40–50 LPM
Min 35 LPM | ≤40°C OUT
Cycle to 10⁻² Pa
~15–22 min
Hot KT-1200 Ready
01 // Vacuum, Gas & Cathodic Arc System Architecture
FIG-01 // P&ID SCHEMATICComplete physical and control topology matching your pit installation, Samkoon HMI (2组 dual backing groups), 4-channel MFCs (Ar / N₂ / C₂H₂), and 22-source SASH arc power rack.
02 // KT-1200 Engineering Blueprints & Machine Spec Placard
FIG-02 // 300 DPI PRINTABLES
External Piping & Internal 4-Stage Supersonic Jets
DOWNLOAD PNG
Print-Ready Machine Spec Sticker (300 DPI)
DOWNLOAD PNG
03 // Pump-Down Telemetry Profile (Atm → 1.0 × 10⁻² Pa)
FIG-03 // LOG-PRESSURE CURVE| Phase | Pressure Envelope | Active Pumping Train | Estimated Time (Hot) |
|---|---|---|---|
| Phase 1: Roughing | 100,000 Pa → 2,000 Pa | 6 × 70 L/s Rotary Vane (420 L/s) | ~1.5 – 2.0 min |
| Phase 2: Roots Cut-In | 2,000 Pa → 5 Pa | 2 × 7.5 kW Roots + 6 × Rotary (~1,200 L/s) | ~5.0 – 8.0 min |
| Phase 3: High Vacuum | 5 Pa → 1.0 × 10⁻² Pa | KT-1200 (50,000 L/s, High-Vac Valve Open) | ~8.0 – 12.0 min |
04 // Power Distribution (72 kW) & 24 kW Heater Plate Schematic
FIG-04 // 380V 3-PHASE05 // Cooling Water & HFV-K3 Oil Specifications
SPEC-05 // FLUIDS| Parameter | Operating Target | Safety / Maintenance Limit |
|---|---|---|
| Oil Type & Quantity | Huifeng HFV-K3 (#3 Mineral) — 22 Liters (5.5 × 4 L cans) | Do NOT mix with silicone oil (275# / DC-704). Change every 3–6 months. |
| Boiler Oil Temp | 230°C – 260°C | Over-temp cutoff at 265°C. Cool < 60–70°C before venting. |
| Cooling Water Flow | 40 – 50 LPM (2.4 – 3.0 m³/h) | Min 35 LPM; interlock must trip 24 kW heater below 35 LPM. |
| Water Temp & Pressure | Inlet: 18–25°C | Pressure: 0.2–0.3 MPa (2–3 bar) | Outlet must stay ≤ 35–40°C (Alarm at 45°C). |
06 // Pre-Flight Launch & Shutdown Checklist
SOP-06 // OPERATOR07 // Site-Specific Inspection Findings (From Your Photos)
AUDIT-07 // ACTION REQUIRED
1. Cracked Top Ceramic Sector on 24 kW Heater Plate: Verify coil-to-pan insulation (MΩ), balance all 3 phase resistances (~6.05 Ω Star / ~18.05 Ω Delta), and replace oxidized terminal ceramic beads before reassembly.
2. Delta Temp Controller Showing
PV: no: Thermocouple is open/disconnected on the front panel unit. Confirm which controller drives the KT-1200 boiler SSR/contactor before powering the 24 kW heater.
3. Purple uPVC Exhaust Manifold & Cabinet Wiring: Ensure purple uPVC exhaust header is ≥ DN100 (110 mm) with an oil-drain trap for the 420 L/s combined rotary exhaust, and bundle loose red wires inside the Siemens PLC / Schneider relay cabinet.